Transforming Land: Construction of the BNSF Logistics Center

TLDRLearn about the ongoing construction of the BNSF Logistics Center in Houston, Texas. This 1500-acre facility is being developed to improve train parking and cargo transportation across the United States. Ames Construction is preparing the site by clearing the land and moving dirt with tractors, scrapers, and trucks. They are also creating ponds to manage stormwater. The project is 60% complete in terms of bulk earthworks, and will soon move on to detail work and infrastructure installation.

Key insights

🚂The BNSF Logistics Center is a 1500-acre facility in Houston, Texas that aims to improve train parking and cargo transportation across the United States.

🚜Ames Construction is responsible for preparing the site, which involves clearing the land and moving dirt using tractors, scrapers, and trucks.

💦Ponds are being created on the site to manage stormwater runoff and retain water during rainy days.

📈The project is currently 60% complete in terms of bulk earthworks, with over 4 million cubic yards of material moved.

🏗️Once the bulk earthworks are finished, the project will move on to detailed work, including road and ditch construction, and infrastructure installation such as paving and rail lines.

Q&A

What is the purpose of the BNSF Logistics Center?

The BNSF Logistics Center aims to improve train parking and cargo transportation across the United States.

Who is responsible for preparing the site?

Ames Construction is responsible for clearing the land, moving dirt, and creating ponds on the site.

What is the current progress of the project?

The project is currently 60% complete in terms of bulk earthworks.

What will happen once the bulk earthworks are finished?

After the bulk earthworks, the project will move on to detailed work, including road and ditch construction, as well as infrastructure installation.

How much material has been moved so far?

Over 4 million cubic yards of material have been moved as part of the project.

Timestamped Summary

00:00Introduction to the BNSF Logistics Center located in Houston, Texas.

00:40Ames Construction is preparing the site by clearing the land and moving dirt with tractors, scrapers, and trucks.

01:08Ponds are being created on the site to manage stormwater runoff and retain water during rainy days.

01:13The project is currently 60% complete in terms of bulk earthworks.

08:47Overview of the double pan system used for hauling and filling.

09:56Explanation of the heaped and struck capacity of the K-Tech pans.

12:06Discussion of the hauling and filling operations on the site.

13:14Closing remarks and appreciation for Ames Construction.